docs(02): complete prompt-control-output-review phase

Phase 2 verified: 16/16 must-haves passed
- PRM-05, UI-05 requirements marked Complete
- Roadmap updated with Phase 2 completion
This commit is contained in:
Michele
2026-03-08 22:36:04 +01:00
parent 14588eaa94
commit d8335585bf
3 changed files with 116 additions and 5 deletions

View File

@@ -132,7 +132,7 @@
| PRM-02 | Phase 1 | Complete |
| PRM-03 | Phase 1 | Complete |
| PRM-04 | Phase 1 | Complete |
| PRM-05 | Phase 2 | Pending |
| PRM-05 | Phase 2 | Complete |
| CSV-01 | Phase 1 | Complete |
| CSV-02 | Phase 1 | Complete |
| CSV-03 | Phase 1 | Complete |
@@ -149,7 +149,7 @@
| UI-02 | Phase 1 | Complete |
| UI-03 | Phase 1 | Complete |
| UI-04 | Phase 1 | Complete |
| UI-05 | Phase 2 | Pending |
| UI-05 | Phase 2 | Complete |
| UI-06 | Phase 3 | Pending |
| UI-07 | Phase 1 | Complete |
| UI-08 | Phase 1 | Complete |
@@ -167,4 +167,4 @@
---
*Requirements defined: 2026-03-07*
*Last updated: 2026-03-08 — Phase 1 requirements marked Complete*
*Last updated: 2026-03-08 — Phase 2 requirements marked Complete*